Hot Water Supply Company: Jilin ShengyuanThermal Power Company
Location: Jilin City Jilin Province
Construction Time: Oct. 2012
Hot Water Supply Area: 5000㎡
Designed Temp.: 65℃
Designed Operation Pressure: 0.4Mpa
Installation Length: 200m
This is the earliest trial project is for new building hot water PERT II piping installation. The whole project adopts PERT II pipes from dn90mm to dn200mm. Up to 2015, three winters passed, the feedback on performance is very good.